LIST OF PRIOR GRANTS:

Non-point Source Pollution Projects Fund

 

PROJECT GRANT AWARDED MAY 2006                         TOTAL: $500,000.00

#20050734                  APPLIED FOR: $500,000.00

AWARDED: $500,000.00

Resource Conservation District

PROJECT: Implementation of Water Quality Improvement Projects in the Gabilan Watershed

DURATION: 36 months                             APPLICANT'S COST MATCH = 35.00%

 

PROJECT GRANTS AWARDED APRIL 2006                    TOTAL:  $614,937.42

#20050437                    APPLIED FOR: $179,543.68          AWARDED: $179,543.00

Agriculture and Land-Based Training Association

PROJECT: Carneros Creek Wetland Restoration and Stream Crossing

DURATION: 36 months                        APPLICANT’S COST MATCH = 28.99%

 

#20050438                    APPLIED FOR: $49,843.42             AWARDED: $49,843.42

Resource Conservation District of Monterey County

PROJECT: Implementation of Irrigation & Nutrient Management Practices

SUMMARY: Work with specific growers to reduce run-off of water, sediments, nutrients, and agricultural chemicals from their crops and land into adjacent waters in northern Monterey County.

DURATION: 36 months                        APPLICANT’S COST MATC = 33.00%

 

#20050439                    APPLIED FOR $50,000.00              AWARDED: $50,000.00

University of California, Santa Cruz

PROJECT: Optimizing Nutrient Management

SUMMARY Work with specific growers to implement best management practices leading to reductions in the quantities of nutrients applied to and running off of their strawberry and vegetable crops in northern Monterey County

DURATION: 24 months                        APPLICANT’S COST MATCH = 25.00%

#20050440                    APPLIED FOR $199,522.70            AWARDED: $199,522.00

University of California, Santa Cruz

PROJECT: Trap cropping in Northern Monterey County strawberry production fields as a non-point pollution prevention strategy

DURATION: 48 months                       APPLICANT’S COST MATCH = 26.41%

#20050732                    APPLIED FOR:  $49,000                   AWARDED:    $49,000

Central Coast Agricultural Water Quality Coalition

PROJECT:  Agricultural Monitoring Data Dissemination and Exceedance Remediation, North Monterey County

DURATION: 30 months                        APPLICANT’S COST MATCH = 25.00+%

 

#20050733                    APPLIED FOR:  $37,030                   AWARDED: $37,030

University of California, Davis

PROJECT:  Reducing nutrient loading from vegetable production at commercial vegetable farms in northern Monterey County

DURATION: 24 months                        APPLICANT’S COST MATCH = 55.90+%

 

#20050735                    APPLIED FOR:  $49,999                   AWARDED: $49,999

California State University, Monterey Bay

PROJECT:  Design Tools for Vegetative Treatment Systems

DURATION: 36 months                        APPLICANT’S COST MATCH = 48.45+%

 

 

PROJECT GRANTS AWARDED MAY 2005                        TOTAL:  $899,889

 

#20040679                    APPLIED FOR:  $49,826                                 AWARDED:    $49,826

Resource Conservation District of Monterey County

PROJECT:  Overcoming Barriers to the Use of Non-crop Vegetation for Water Quality Improvement

SUMMARY:  Educational outreach and on-site implementation of NSP abatement.

DURATION:  36 months                       APPLICANT’S COST MATCH = +24.88%

 

#20040680                   APPLIED FOR:  $49,893                                 AWARDED:    $49,893

Resource Conservation District of Monterey County

PROJECT:  Elkhorn Slough Watershed: Underground Pipe Installation & Sediment Basin Construction

SUMMARY:  On-site implementation of NSP abatement in the Project watershed.

DURATION:  24 months                       APPLICANT’S COST MATCH = 62.26%

 

#20040681                    APPLIED FOR:  $49,883                                 AWARDED:    $49,883

Resource Conservation District of Monterey County

PROJECT:  Moro Cojo-Santa Rita Creek: Underground Pipe Installation & Sediment Basin Retrofits

SUMMARY:  On-site implementation of NSP abatement in the Project watershed.

DURATION:  24 months                       APPLICANT’S COST MATCH = +35.33%

 

#20040682                   APPLIED FOR:  $49,870                                 AWARDED:    $49,870

Resource Conservation District of Monterey County

PROJECT:  Carneros Creek: Underground Pipe Installation & Sediment Basin Construction

SUMMARY:  On-site implementation of NSP abatement in the Project watershed.

DURATION:  24 months                       APPLICANT’S COST MATCH = 29.95%

 

#20040683                   APPLIED FOR:  $200,000                               AWARDED:    $200,000

Community Alliance with Family Farmers

PROJECT:  Implementation of Agricultural Vegetative Management Practices

SUMMARY:  Educational outreach and on-site implementation of vegetative projects.

DURATION:  36 months                       APPLICANT’S COST MATCH = +30.63%

 

#20040684                    APPLIED FOR:  $320,000                               AWARDED:    $320,000

Agricultural Land-based Training Association

PROJECT:  Outreach and Education on Practices to Enhance Water Quality

SUMMARY:  Educational outreach about non-point source pollution from agricultural sources.

DURATION:  24 months                       APPLICANT’S COST MATCH = 25.82%

 

#20040686                    APPLIED FOR:  $180,417                               AWARDED:    $180,417

Coastal Watershed Council

PROJECT:  Facilitation of Self-monitoring for Water Quality by Growers

SUMMARY:  Educational outreach about non-point source pollution from agricultural sources.

DURATION:  31 months                       APPLICANT’S COST MATCH = 30.93%

 

PROJECT GRANTS AWARDED DECEMBER 2004                        TOTAL:  $403,591

 

#20040574                    APPLIED FOR: $71,376                                  AWARDED:    $71,376

University of California Cooperative Extension, San Luis Obispo County

PROJECT:  Farm Water Quality Improvement Projects

SUMMARY:  Teach Farm Water Quality Short Courses in the lower Salinas and Elkhorn Slough.

DURATION:  24 months                 APPLICANT’S COST MATCH = 33.67%

 

#20040575                    APPLIED FOR: $282,290                                AWARDED:    $282,290

Resource Conservation District of Monterey County

PROJECT:  Agricultural Conservation Projects

SUMMARY:  Provide technical assistance to watershed working groups and other growers in the lower Salinas and Elkhorn Slough.

DURATION:  36 months                 APPLICANT’S COST MATCH = 50.06%

 

#20040576                    APPLIED FOR: $49,925                                  AWARDED:    $49,925

Resource Conservation District of Monterey County

PROJECT:  Gully Erosion Stabilization Projects

SUMMARY:  Arrest erosion of at least three active gullies on slopes in Elkhorn Slough watershed.

DURATION:  24 months                 APPLICANT’S COST MATCH = 55.52%